Alberta Transportation and Economic Corridors Gordon E. Taylor Bridge Construction
Posted on Mar. 28 2025
Highway 9 (Bridge Street) within the Town of Drumheller
Overview
Beginning Spring 2024, Alberta Transportation and Economic Corridors will start construction on the Gordon E. Taylor bridge on Highway 9 (Bridge Street) over the Red Deer River within the Town of Drumheller.
Project Details
Construction on the Gordon E. Taylor bridge will begin May 2024. The bridge rehabilitation work consists of widening the clear bridge width as well as modifications to the existing roadways and connecting pathways at the bridge approaches. Construction is expected to take two (2) years to complete, with an anticipated completion date of Fall 2025, weather permitting. Work will take place on site between the hours of 7 am and 7 pm daily, 5 days a week. If night work is required, information will be posted on site prior to commencement.
See the Government of Alberta full info sheet here